Two Bids Received for Airport Runway Expansion

The BVI Airports Authority has received two tenders for the first phase of the airport runway extension project. The initial phase will add 787 feet to the western end of the runway, laying the groundwork for an eventual 7,000-foot runway. Officials expect the contract to be awarded in December following technical and financial evaluations.

· Updated

The BVI Airports Authority has officially received two tenders for the west runway extension project at the Terrance B. Lettsome International Airport, Minister for Communications and Works Hon. Rymer announced in the House of Assembly. The project marks the first phase of a comprehensive development initiative aimed at ultimately lengthening the territory's main airport runway to approximately 7,000 feet.

Under this initial phase, 787 feet will be added to the western end of the existing runway, providing immediate relief for commercial air operations. According to Minister Rymer, the open and competitive procurement process was conducted under tender reference BVIAA/RFP/2026/WRE-01.

An evaluation team is currently reviewing the technical submissions, after which the financial proposals will be unsealed and the tendered prices formally evaluated in line with standard public procurement guidelines. Minister Rymer emphasized the strategic value of the project to the Virgin Islands' aviation sector and wider economy.

The extended runway will enable commercial aircraft to operate with reduced weight and payload restrictions, which in turn will support greater passenger numbers, higher cargo capacity, and improved overall operational reliability. The Minister also assured legislators and residents that the multi-million-dollar undertaking is being managed with integrity and transparency.

He highlighted that the project belongs to the people of the Virgin Islands and noted that the Airports Authority remains committed to facilitating meaningful participation by local contractors, skilled tradespeople, and domestic service providers wherever practicable. Premier and Minister of Finance Dr. the Hon.

Wheatley has previously stated that the formal contract for the runway extension is scheduled to be awarded in December.

Primary source: VINO